Weekly Update 9th February

Weekly Update 9th February

Construction activity for the week included;

  • 13 of 53 WTG now complete. 24 WTG base and mid tower sections erected.
  • 46% of the turbine components (blades, hubs, towers) delivered to site.
  • 45 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.
  • Continuation of earthworks for turbine access roads; approximately 88% of clearance works complete
  • Construction of substation and switchyard continuing. Placement of underground cabling continuing
  • Works continue on upgrades to Site Entry Road (intersection to site compound) including vegetation of batters
  • UXO, Cultural Heritage and Environmental aspects continue prior to vegetation clearance in new areas.
  • Weed contractor has commenced to address issues following recent rainfall.
  • 76 pieces of heavy equipment on-site.
  • Personnel on-sit eaveraged 212.
MEWF Weekly Update 9th February
📄