Mt Emerald Wind Farm

Weekly Update 30th March

Weekly Update 30th March

Construction activity for the week included;

  • 22 of 53 WTG now complete. 28 WTG base and mid tower sections erected.
  • 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather.
  • 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.
  • Continuation of earthworks for turbine access roads; approximately 93% of clearance works complete
  • Construction of substation and switchyard continuing.
  • Placement of underground cabling continuing.
  • Works continue on upgrades to Site Entry Road (intersection to site compound) including vegetation of batters
  • UXO, Cultural Heritage and Environmental aspects continue prior to vegetation clearance in new areas.
  • Weed contractor has commenced to address issues following recent rainfall.
  • Personnel on-site averaged 238.
  • Site impacted by rainfall. Average March rainfall is 205mm, with March 2018 receiving 518mm, with over 100mm in one night (26th) this week.
MEWF Weekly Update 30th March
📄