24 hour community call line: 1800 280 013
Mt Emerald Wind Farm

Weekly Update 10th May

Weekly Update 10th May

Construction activity for the week included;
• Site Entry Road (from base of hill to top) earthworks continues
• Commencement of earthworks for turbine access roads for WTG 34-39, 40-42 and 24
• Bulk earthworks at Powerlink substation bench
• Rock crushing and screening commenced at Upper Laydown Area
• Geotechnical investigation of remaining turbine foundations
• Field survey work continues for UXO, Cultural Heritage and Environmental aspects prior to vegetation clearance in new areas
• Over 50 Northern Quolls have now had tracking collars fitted to allow for clearance before works are started
• Equipment on-site 22 units - rollers, excavators, water & dump trucks, dozers, drill rigs, graders
• Average personnel on-site for week - 53; 115 people inducted

MEWF Weekly Update 10th May
📄
Download the document: 20170510-MEWF-Weekly-Update.pdf
← Weekly Update 3rd MayWeekly Update 17th May →