Weekly Update 15th March
No new ground disturbance/clearing works were conducted during this period. Current Clearing Allowance used - 2.8% Cultural Heritage team continued with clearance survey of areas along the access track alignment progressing from approximately WTG 40 through to WTG 51. Work on the site compound is…
Read more »Weekly Update 8th March
• Site establishment and vegetation clearing along access track alignment has continued. Additional areas have been handed over to the Contractor after completion of the environmental, UXO and cultural assessments. • Activities at the Powerlink Queensland (PLQ) substation bench have commenced, wi…
Read more »Media Release: Ratch promotes local participation in Mount Emerald Wind Farm.
Media Release 22 February 2017 Ratch promotes local participation in Mount Emerald Wind Farm. Construction has commenced on the $360 million Mount Emerald Wind Farm with several businesses from the wider Cairns region already engaged to conduct preliminary works ahead of more expansive works afte…
Read more »MEWF Newsletter #11, February 2017
Please find the latest Mt Emerald Wind Farm Newsletter. MEWF - Newsletter #11 - Feb 2017
Read more »Feb 2017: Letters of Consent received from Government to begin
Early works commenced February 14th on the transport depot laydown area at the base of the site. All pre-start UXO, Cultural Heritage and Environmental surveys have been conducted to verify the site is ‘ready to go’. Flagging of works area has occurred to limit the extent of clearing, in preparat…