Weekly Update 23rd March
Construction activity for the week included; 21 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Internal road repairs completed to allow deliveries to tower sites. Port-Site deliveries remain on- hold due to wet weather. 50 of 53 foundations poured.…