Weekly Update 6th April
Construction activity for the week included; 23 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…
Weekly Update 30th March
Construction activity for the week included; 22 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…