Weekly Update 7th June

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to top) earthworks…

Weekly Update 31st May

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to top) earthworks…

Weekly Update 24th May

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant transported onto site to allow use of excavated rock as roadbase or compacted fill • Water stand set-up (extraction point) • Site Entry Road (from base of hill to top) earthworks continues • Continuation of…

Weekly Update 17th May

Construction activity for the week included; • Main access road maintenance • Drilling activities • Water stand set-up (extraction point) • Main compound fencing and undercover roof area • Bulk earthworks at Powerlink substation bench • Site Entry Road (from base of hill to top) earthworks continues • Continuation of earthworks for turbine access roads…

Weekly Update 10th May

Construction activity for the week included; • Site Entry Road (from base of hill to top) earthworks continues • Commencement of earthworks for turbine access roads for WTG 34-39, 40-42 and 24 • Bulk earthworks at Powerlink substation bench • Rock crushing and screening commenced at Upper Laydown Area • Geotechnical investigation of remaining turbine…

Weekly Update 3rd May

Construction activity for the week included; • Site Entry Road (from base of hill to top) – earthworks for chainage 0400 – 1500 • Commencement of earthworks for turbine access roads for WTG 36-53 • Bulk earthworks at Powerlink substation bench • Bulk earthworks at Upper Laydown Area • Geotechnical investigation of remaining turbine foundations…

Weekly Update 26th April

Construction activity for the week included; • Main access road – clearing and grubbing, profiling, sub-base works for Chainage 400 – 1700 • Commencement of earthworks for upper laydown area • Excavation of the first wind turbine foundation (WTG#3) • Bulk earthworks commenced for Powerlink bench for connection to the electricity grid • Clearing of…

Weekly Update 19th April

Construction activity for the week included; • Main access road – clearing and grubbing, profiling, sub-base works • Excavation of the first wind turbine foundation (WTG#3) • Clearing and profiling of the Powerlink bench for connection to the electricity grid • Clearing of spur roads to wind turbine locations from main access road • Clearing,…

Weekly Update 12th April

• Works continued on the construction of the main access road to the Mount Emerald Wind Farm site. • Excavation commenced for the first wind turbine foundation. • Clearance activities have also commenced for hardstand areas around the first nine wind turbines. • All the buildings at the temporary site compound are now completed and…