Weekly Update 6th April

Construction activity for the week included; 23 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…

Weekly Update 30th March

Construction activity for the week included; 22 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…

Weekly Update 23rd March

Construction activity for the week included; 21 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Internal road repairs completed to allow deliveries to tower sites. Port-Site deliveries remain on- hold due to wet weather. 50 of 53 foundations poured.…

Weekly Update 16th March

Construction activity for the week included; 21 of 53 WTG now complete. 27 WTG base and mid tower sections erected. 51% of the turbine components (blades, hubs, towers) delivered to site. Deliveries on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.…