Weekly Update 16th February

Construction activity for the week included; 15 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 48 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 9th February

Construction activity for the week included; 13 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 45 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 2nd February

Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 12 of 53 WTG now complete. 23 WTG base and mid tower sections erected. 41% of the turbine components (blades, hubs, towers) delivered to site. 44 of 53 foundations poured. Excavation and preparation of foundations…