Weekly Update 16th February
Construction activity for the week included; 15 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 48 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…