Weekly Update 8th March
• Site establishment and vegetation clearing along access track alignment has continued. Additional areas have been handed over to the Contractor after completion of the environmental, UXO and cultural assessments. • Activities at the Powerlink Queensland (PLQ) substation bench have commenced, with vegetation clearing complete and bulk earthworks set to commence. • Further levelling of…