Weekly Update 30th August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 7 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of…

Weekly Update 23rd August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. 4 of 53 foundations poured. Continuation of earthworks for turbine access roads; approximately 47% of clearance works complete. Local supplier…

Weekly Update 16th August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. First foundation (WTG #4) poured 11th August. Placing of reinforcing continuing at WTG 5, 7 and 8. Continuation of earthworks…