• Construction of the site compound was the focal point of activity.
• Levelling of the site compound hard stand area continued while more office facilities were installed and a carpark established. Compound electrical and plumbing works have commenced and temporary power is in place.
• Concurrent with vegetation clearing, sediment controls are being progressively implemented across the site with some repairs completed following rain events.
• Preparation of the main entry road and access tracks is ongoing.
• As part of our rigorous weed control operation, a temporary washdown facility has been set up for all vehicles, machinery and plant moving between locations.
• Daily environmental inspections are being conducted.
• The trapping / tracking campaign for Northern Quoll continues