Weekly Update 23rd August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. 4 of 53 foundations poured. Continuation of earthworks for turbine access roads; approximately 47% of clearance works complete. Local supplier…

Weekly Update 16th August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. First foundation (WTG #4) poured 11th August. Placing of reinforcing continuing at WTG 5, 7 and 8. Continuation of earthworks…

Weekly Update 26th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. Crushing of cap delayed due to Quoll in rack stockpile. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Continuation of earthworks…

Weekly Update 19th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Site roads and hardstand for WTG 6-9 underway with placement of road base occurring…

Weekly Update 14th June

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • 2 x Crushing plants established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to…

Weekly Update 7th June

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to top) earthworks…

Weekly Update 31st May

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to top) earthworks…

Weekly Update 24th May

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant transported onto site to allow use of excavated rock as roadbase or compacted fill • Water stand set-up (extraction point) • Site Entry Road (from base of hill to top) earthworks continues • Continuation of…

Weekly Update 17th May

Construction activity for the week included; • Main access road maintenance • Drilling activities • Water stand set-up (extraction point) • Main compound fencing and undercover roof area • Bulk earthworks at Powerlink substation bench • Site Entry Road (from base of hill to top) earthworks continues • Continuation of earthworks for turbine access roads…

Weekly Update 10th May

Construction activity for the week included; • Site Entry Road (from base of hill to top) earthworks continues • Commencement of earthworks for turbine access roads for WTG 34-39, 40-42 and 24 • Bulk earthworks at Powerlink substation bench • Rock crushing and screening commenced at Upper Laydown Area • Geotechnical investigation of remaining turbine…