Weekly Update 20th December

Construction activity for the week included; Site shutdown from 22-12-2017 to 3-01-2018, with full operation resuming 8-01-2018. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine…

Weekly Update 13th December

Construction activity for the week included; 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 41 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine access roads; approximately 74% of clearance works complete Construction of substation…

Weekly Update 6th December

Construction activity for the week included; 5 of 53 WTG now complete (WTG 3,4,5,8,9) with WTG 6, 7, 14 and 15 expected in next two weeks. 40 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access roads; approximately 74% of clearance…

Weekly Update 29th November

Construction activity for the week included; 3 of 53 WTG now complete (WTG 3,4,5) with WTG 9, 8, 7 and 6 expected in next two weeks. 38 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine access roads; approximately 71% of clearance…

Weekly Update 15th November

Construction activity for the week included; Tower erection – tower and hub installed at WTG 5. High winds preventing blade install. Base and mid tower section installed at WTG 3, 4 and 9. 34 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for…

Weekly Update 27th September

Construction activity for the week included; Powerlink commenced construction activities for substation infrastructure. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 18 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues. Continuation of earthworks for…

Weekly Update 20th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 16 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 13th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 13 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 6th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 9 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 30th August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 7 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of…