Weekly Update 23rd March

Construction activity for the week included; 21 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Internal road repairs completed to allow deliveries to tower sites. Port-Site deliveries remain on- hold due to wet weather. 50 of 53 foundations poured.…

Weekly Update 16th March

Construction activity for the week included; 21 of 53 WTG now complete. 27 WTG base and mid tower sections erected. 51% of the turbine components (blades, hubs, towers) delivered to site. Deliveries on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.…

Weekly Update 9th March

Construction activity for the week included; 20 of 53 WTG now complete. 27 WTG base and mid tower sections erected. 51% of the turbine components (blades, hubs, towers) delivered to site. Deliveries on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.…

Weekly Update 2nd March

Construction activity for the week included; 18 of 53 WTG now complete. 26 WTG base and mid tower sections erected. 49% of the turbine components (blades, hubs, towers) delivered to site. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 23rd February

Construction activity for the week included; 17 of 53 WTG now complete. 25 WTG base and mid tower sections erected. 47% of the turbine components (blades, hubs, towers) delivered to site. 49 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 16th February

Construction activity for the week included; 15 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 48 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 9th February

Construction activity for the week included; 13 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 45 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 2nd February

Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 12 of 53 WTG now complete. 23 WTG base and mid tower sections erected. 41% of the turbine components (blades, hubs, towers) delivered to site. 44 of 53 foundations poured. Excavation and preparation of foundations…

Weekly Update 19th January

Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access roads; approximately 78% of clearance works complete Construction of substation and…

Weekly Update 12th January

Construction activity for the week included; Partial site activities commenced on 3rd January, with full operation commencing 8th January. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks…