Weekly Update 27th September

Construction activity for the week included; Powerlink commenced construction activities for substation infrastructure. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 18 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues. Continuation of earthworks for…

Weekly Update 20th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 16 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 13th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 13 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 6th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 9 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 30th August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 7 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of…

Weekly Update 23rd August

Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. 4 of 53 foundations poured. Continuation of earthworks for turbine access roads; approximately 47% of clearance works complete. Local supplier…

Weekly Update 26th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. Crushing of cap delayed due to Quoll in rack stockpile. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Continuation of earthworks…

Weekly Update 19th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Site roads and hardstand for WTG 6-9 underway with placement of road base occurring…

Weekly Update 14th June

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • 2 x Crushing plants established to allow use of excavated rock as roadbase or compacted fill • Water stand (extraction point) in use allowing for increased dust suppression • Site Entry Road (from base of hill to…