Weekly Update 16th February

Construction activity for the week included; 15 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 48 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 9th February

Construction activity for the week included; 13 of 53 WTG now complete. 24 WTG base and mid tower sections erected. 46% of the turbine components (blades, hubs, towers) delivered to site. 45 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…

Weekly Update 2nd February

Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 12 of 53 WTG now complete. 23 WTG base and mid tower sections erected. 41% of the turbine components (blades, hubs, towers) delivered to site. 44 of 53 foundations poured. Excavation and preparation of foundations…

Weekly Update 19th January

Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access roads; approximately 78% of clearance works complete Construction of substation and…

Weekly Update 12th January

Construction activity for the week included; Partial site activities commenced on 3rd January, with full operation commencing 8th January. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks…

Weekly Update 20th December

Construction activity for the week included; Site shutdown from 22-12-2017 to 3-01-2018, with full operation resuming 8-01-2018. 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine…

Weekly Update 13th December

Construction activity for the week included; 6 of 53 WTG now complete. Additional 16 WTG base and mid tower sections erected. 41 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine access roads; approximately 74% of clearance works complete Construction of substation…

Weekly Update 6th December

Construction activity for the week included; 5 of 53 WTG now complete (WTG 3,4,5,8,9) with WTG 6, 7, 14 and 15 expected in next two weeks. 40 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access roads; approximately 74% of clearance…

Weekly Update 29th November

Construction activity for the week included; 3 of 53 WTG now complete (WTG 3,4,5) with WTG 9, 8, 7 and 6 expected in next two weeks. 38 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine access roads; approximately 71% of clearance…

Weekly Update 15th November

Construction activity for the week included; Tower erection – tower and hub installed at WTG 5. High winds preventing blade install. Base and mid tower section installed at WTG 3, 4 and 9. 34 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for…