Weekly Update 6th April
Construction activity for the week included; 23 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…
Weekly Update 30th March
Construction activity for the week included; 22 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Port-Site deliveries remain on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured…
Weekly Update 23rd March
Construction activity for the week included; 21 of 53 WTG now complete. 28 WTG base and mid tower sections erected. 53% of the turbine components (blades, hubs, towers) delivered to site. Internal road repairs completed to allow deliveries to tower sites. Port-Site deliveries remain on- hold due to wet weather. 50 of 53 foundations poured.…
Weekly Update 16th March
Construction activity for the week included; 21 of 53 WTG now complete. 27 WTG base and mid tower sections erected. 51% of the turbine components (blades, hubs, towers) delivered to site. Deliveries on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.…
Weekly Update 9th March
Construction activity for the week included; 20 of 53 WTG now complete. 27 WTG base and mid tower sections erected. 51% of the turbine components (blades, hubs, towers) delivered to site. Deliveries on-hold due to wet weather. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues.…
Weekly Update 2nd March
Construction activity for the week included; 18 of 53 WTG now complete. 26 WTG base and mid tower sections erected. 49% of the turbine components (blades, hubs, towers) delivered to site. 50 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access…