Weekly Update 19th January
Construction activity for the week included; 8 of 53 WTG now complete. 22 WTG base and mid tower sections erected. 44 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues. Continuation of earthworks for turbine access roads; approximately 78% of clearance works complete Construction of substation and…