Weekly Update 24th May
Construction activity for the week included; • Bulk earthworks at Powerlink substation bench key activity this week • Crushing plant transported onto site to allow use of excavated rock as roadbase or compacted fill • Water stand set-up (extraction point) • Site Entry Road (from base of hill to top) earthworks continues • Continuation of…