Construction activity for the week included; Tower erection –WTG 5 installation complete 17/11/17. Base and mid tower section installed at WTG 6 and 7. 34 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for turbine access roads; approximately 61% of clearance works complete…

Weekly Update 15th November

Construction activity for the week included; Tower erection – tower and hub installed at WTG 5. High winds preventing blade install. Base and mid tower section installed at WTG 3, 4 and 9. 34 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling and earthing of poured foundations continues Continuation of earthworks for…