Weekly Update 27th September

Construction activity for the week included; Powerlink commenced construction activities for substation infrastructure. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 18 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues. Continuation of earthworks for…

Weekly Update 20th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 16 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 13th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 13 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…

Weekly Update 6th September

Construction activity for the week included; Earthworks at Powerlink substation bench complete. Powerlink taking over and established site. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 9 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of poured foundations continues.…