Weekly Update 30th August
Construction activity for the week included; Earthworks at Powerlink substation bench now complete, with final proof rolling of capping layer. Site Access Road. Road up the hill is now open to be used for access. Base material being placed for final profiling. 7 of 53 foundations poured. Excavation and preparation of foundations continuing. Backfilling of…