Weekly Update 26th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. Crushing of cap delayed due to Quoll in rack stockpile. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Continuation of earthworks…

Weekly Update 19th July

Construction activity for the week included; • Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. • Site Access Road. Road up the hill is nearing a point where it can now be used for access. • Site roads and hardstand for WTG 6-9 underway with placement of road base occurring…