Weekly Update 3rd May

Construction activity for the week included; • Site Entry Road (from base of hill to top) – earthworks for chainage 0400 – 1500 • Commencement of earthworks for turbine access roads for WTG 36-53 • Bulk earthworks at Powerlink substation bench • Bulk earthworks at Upper Laydown Area • Geotechnical investigation of remaining turbine foundations…