Weekly Update 26th April

Construction activity for the week included; • Main access road – clearing and grubbing, profiling, sub-base works for Chainage 400 – 1700 • Commencement of earthworks for upper laydown area • Excavation of the first wind turbine foundation (WTG#3) • Bulk earthworks commenced for Powerlink bench for connection to the electricity grid • Clearing of…