Weekly Update 19th April
Construction activity for the week included; • Main access road – clearing and grubbing, profiling, sub-base works • Excavation of the first wind turbine foundation (WTG#3) • Clearing and profiling of the Powerlink bench for connection to the electricity grid • Clearing of spur roads to wind turbine locations from main access road • Clearing,…