Weekly Update 15th March

No new ground disturbance/clearing works were conducted during this period. Current Clearing Allowance used – 2.8% Cultural Heritage team continued with clearance survey of areas along the access track alignment progressing from approximately WTG 40 through to WTG 51. Work on the site compound is continuing with land being cleared ahead of site offices being…

Weekly Update 8th March

• Site establishment and vegetation clearing along access track alignment has continued. Additional areas have been handed over to the Contractor after completion of the environmental, UXO and cultural assessments. • Activities at the Powerlink Queensland (PLQ) substation bench have commenced, with vegetation clearing complete and bulk earthworks set to commence. • Further levelling of…