Skip to content
Mt Emerald Wind FarmMt Emerald Wind Farm
Mt Emerald Wind Farm
  • The Project
  • Community
  • Construction
  • Compliance
  • FAQ’s
  • News
  • Employment
  • Contact
  • The Project
  • Community
  • Construction
  • Compliance
  • FAQ’s
  • News
  • Employment
  • Contact

Welcome to…

Mount Emerald Wind Farm

Latest News
  • MEWF November 2017 Newsletter

    30th November 2017
    MEWF – Newsletter #16 – November 2017Read More »
  • MEWF October 2017 Newsletter

    16th October 2017
    MEWF – Newsletter #15 – October 2017Read More »
  • Critical elements complete 26/07/2017

    13th August 2017
    Bulk earthworks at Powerlink substation bench now complete. Placement of final capping layer remains. Crushing of cap delayed due to …Read More »

Ratch Australia is building the $380M Mt Emerald Wind Farm on 2400Ha of private land on the plateau adjacent to the Mt Emerald/ Springmount area. Approx ½ way between Mareeba and Atherton. 5km west of Walkamin.

We will build 53 wind turbines generating up to 180.5 MW of power from this site:MEWF-Internal-Roads-Map-Sept2016_sm

  • 37* 3.45MW turbines will have 117m diameter rotor on a 90m tower
  • 16* 3.3MW turbines will have 112m diameter rotor on an 84m tower

Turbine blades will be 57m long.

This will supply on average 1/3 of the power needs of Far North Queensland.

Mt Emerald Wind Farm developer RATCH Australia, has created this website site to inform the community of progress as construction occurs and answer many of the questions that are raised by the communities in which wind farms are proposed and operated.

Under each of the headings are a series of questions answered with the latest local, national and international information available, including summaries of results of EIS studies that have been conducted specific to the site.

Actual reports of the EIS and other more technical information relative to the project is available at: www.ratchaustralia.com/

This site will be updated regularly as the new information becomes available. If you have any questions or requests for additional information, please use our contact form here.

Project Overview

Mt Emerald Wind Farm is a ‘greenfield wind farm development’ meaning that the land upon which the wind farm is located has had no previous commercial land-use.

Development has been approved for up to 63 turbines at this site – however only 53 are to be constructed. A reduction in the number of turbines from the original proposed 75, is a result of:

  • community consultation and site assessment;
  • discussion with government and other key stakeholders;
  • to locate the turbines to avoid quoll habitat, and move some turbines from prominent ridgelines to reduce the visual and cultural heritage impact of the site works.
  • Estimated Construction Cost ~ $380 – $400 Million.
  • Estimated Annual Generation will be 500-600 GWh per annum, which will generate electricity to power the average use of 75,000 – 90,000 homes (1/3 of homes in FNQ)
  • Approximately 40km of new site roads will be required to bring the turbines to site safely, and to connect the turbines once constructed.
  • To enable connection to the existing 275kV NEM Powerlink Transmission line, which traverses the site, a new 33/275kV substation and switching yard will be constructed. Adjacent to the sub-station, a dedicated on-site O&M compound and control room will also be built for RATCH operational staff.

Why here?

The land comprises 2400Ha, whose orientation and elevation make it ideal as a wind farm.

  • It has an excellent wind resource
  • There are relatively few residences near the site
  • It is close to the electricity grid, reducing the length of the transmission line
  • EIS studies show minimal environmental and social impact

The site land is a rough plateau (elevation 900m) elevated approx 300m above the surrounding plains and is comprised of sparse natural scrubland with some rocky outcrops. The property is currently not used for any particular activity. The surrounding land is predominantly used for agriculture and grazing. The local landmark, Mt Emerald (elevation 1122m) is roughly 2km from the southern boundary of the site.

Project Delivery Timeline

November 2016

Sunwater pipeline works at Kippen Drive intersection. All financing secured for project

Feb 2017

Vestas formally handed site. Preliminary construction works begin - road upgrades, site office erection.

April 2017

Construction of wind farm to begin with earthworks.

October 2017

Wind Turbine components will commence being delivered to site.

December 2017

All road works complete. All concrete foundations for turbines complete.

May 2018

Substation is completed and wind farm is connected to the grid network.

August 2018

All Turbines are erected.

September 2018

We flick the switch. Full commercial operations.

Project Newsletters

MEWF November 2017 Newsletter
30th November 2017
MEWF October 2017 Newsletter
16th October 2017
MEWF – Newsletter #14 – August 2017
13th August 2017
MEWF – Newsletter #13 – June 2017
13th August 2017
MEWF – Newsletter #12 – April 2017
1st May 2017

Read More >>

Community

Local Procurement

Local procurement has commenced, with: • Koppens and Mareeba Crane Hire constructing the concrete culvert to protect the irrigation channel during December 2016. • A new vehicle purchased from Mareeba Toyota, January 2017 • Contracting of the MBarBarrum Aboriginal Corporation to undertake Cultural Heritage surveys and assist with environmental surveys during the entire construction period.…

3rd March 2017

Read More >>

Project and Compliance Updates

Feb 2017: Letters of Consent received from Government to begin

Early works commenced February 14th on the transport depot laydown area at the base of the site. All pre-start UXO, Cultural Heritage and Environmental surveys have been conducted to verify the site is ‘ready to go’. Flagging of works area has occurred to limit the extent of clearing, in preparation for pad establishment. Letters of…

3rd March 2017

Read More >>


www.ratchaustralia.com


Contact details for RATCH-Australia offices:

Brisbane Office: 07 3214 3400

Address: PO Box 12833, George Street Qld 4003



Sydney Office: 02 8913 9400

Address: PO Box 1058, North Sydney NSW 2059




24 hour community call line: 1800 702 597

Project email address: info@mtemeraldwindfarm.com.au

Project mailing address: PO Box 1058, North Sydney NSW 2060

Contact Us

Submitclear

Mt Emerald Wind Farm. 2016 (c)